Close a project

A project cannot be deleted due to demands for keeping an intact audit trail within KI ELN.
However, a project can be closed if the research project is finished or if it was created by mistake.

A closed project will still be shown in the ELNAdminWeb and the experiments of the project will still appear in ELN.

However, new experiments cannot be added to a closed project.

The closed project will not appear on the projects list when trying to choose a project for an experiment on ELN.

A closed project can always be re-opened and its experiments remain intact.

To close a project:

Go to “Projects”

Select the project you want to close.

ELNAdminWeb close project

Select the box “Closed”

Click “Save”.

ELNAdminweb close project
02-12-2022